Senate Standing Committee on Communications 

Islamabad, November 12, 2021 (PPI-OT):A Sub-committee of the Senate Standing Committee on Communications to investigate the difference between estimated cost and completion cost of the completed/ongoing projects worth more than rupees one Billion (increased cost projects) during the period from June 2008 to June 2021 was held under the convener ship of Senator Saifullah Abro here at the Parliament House on Thursday.

The meeting was attended by Kamil Ali Agha along with the senior officials of the Ministry of Communications and National Highways Authority (NHA). At the outset of the meeting, the officials of the NHA presented a report of over 30,000 pages along with a briefing on projects completed at an increased cost.

Convener committee pointed out that in the report of 30,000 pages the main receipt of PC-1 is missing. He expressed his desire to present the report in a tabulated form, which will bring clarity to the report. The convener committee also pointed out that the report is not according to the Proforma prepared by Senator Kamil Ali Agha and the sequence is also not followed.

He said that there is some wisdom according to which the sequence has been made in the proforma which should be diligently followed. The committee also directed the ministry to depute a technical expert in order to evaluate the report. Earlier, in the meeting, discussion on the approach road of Larkana-Khairpur Bridge Project on Larkana side, PC-1 was also discussed.

The committee was informed of the reasons for the cost overrun. The committee was also apprised that originally bridge was designed and tendered for 2 lanes with 22 spans for discharge of 8 lac Cusec of water which was changed to two lanes with 26 spans for discharge of 12 lac Cusec of water. Also, a revised Hydraulic Model Study which was conducted in 2010 recommended river training works due to super flood.

The committee was also informed that one of the reasons for the cost overrun was due to release of insufficient funds vis-a-vis the Financial Phasing of the Project in PC-1 and delay approval of revised PC-1. The committee was informed that due to enhancement of cost the PC-1 was revised from Rs/- 9,225.339 million to Rs.13, 397 million, presented before ECNEC and was approved on 22-04-2016. The project has been completed within the cost of approved PC-1. The revised cost design has been regularized after approval of PC-1 by the ECNEC.

For more information, contact:
Senate of Pakistan
H.No.7, Cat-II, G-8/2, Islamabad, Pakistan
Tel: +92-51-9204564534
Fax: +92-51-9205703
E-mail: senate@comsats.net.pk
Website: www.senate.gov.pk

Recent Posts